Issue materials when you take stock out for a production job. For example, if a work order needs fabric and lining, record the quantity of each material you hand over to production.
Review suggested quantities
- Open Production → Work Orders, find the work order and open Assignments / History.
- Select Actions → Issue materials.
- If BOM suggestions appears, expand it. The suggested quantity is for this work-order unit and includes wastage. Check Remaining to see how much of the suggested quantity is still outstanding.
Record the actual stock issued
- Check the work-order number and Document date. Add a Reason, reference or notes if the team needs more context about the issue.
- Select + Add item and choose the stock item you are issuing.
- Enter the actual quantity being issued. Repeat for each material. For example, if the BOM suggests 3 metres of fabric and you hand over 2 metres today, issue 2 metres now. You can record the rest when it is handed over.
- Review the stock items and quantities, then select Issue materials. Wait for the Materials issued. confirmation before closing the dialog.
If you can’t issue a material
If a BOM suggestion shows a stock setup problem, read the message under that material and have the stock setup checked before issuing it. If Issue materials is missing or unavailable, check that you’re working at the work order’s location and ask your workspace administrator to check your stock issue access.