Record the start and finish of an assigned production stage so the team can see where the work stands. For example, mark cutting finished when the pieces are ready for review.

Start the assigned work

  1. Open Production → Work Orders and find the work order.
  2. Open Assignments / History and find the assigned stage. Check the worker’s name before taking action.
  3. Select Start work. Add Remarks if there is anything the team needs to know.
  4. Confirm the action. If approval is required, enter an Approval reason and select Request approval.

Mark the stage finished

  1. Return to the stage in Assignments / History.
  2. Select Mark finished to open Finish work.
  3. Enter Worked minutes if you want to record the time spent. Use whole minutes, such as 45 for 45 minutes. Add Remarks for details the reviewer should know.
  4. Confirm the action. If prompted, enter an Approval reason and select Request approval.

Check the completion status

If the stage is submitted for completion review, return to Assignments / History to check the outcome. A user with the appropriate access can select Approve completion or Reject completion. If completion is rejected, review the reason before assigning the stage again.

If a stage action is missing

Check the stage’s current status. Start work is available for an eligible assignment that has yet to start, and Mark finished is available once the assignment is in progress. Check whether the work order is on hold or at another working location. If the stage is ready and you still cannot see the action, ask your workspace administrator to check your access.