Use the work order’s stage history to see who is doing the work, when it started and what still needs attention.

Open the production stages

  1. Open Production → Work Orders and find the work order.
  2. If the list tells you to switch to another location to view the stages, switch to the location shown.
  3. Open Assignments / History on the work order. Find the stage you want to update.

Assign a worker and record progress

  1. Select Assign work for the stage when available. Choose the worker and enter the expected finish details if prompted.
  2. If the assignment is sent for approval, check the stage history once the request has been reviewed.
  3. When the worker begins, select Start work on the assignment.
  4. When the stage work is done, select Mark finished. If the app submits the work for completion review, check the stage again after it has been reviewed.

Review completion and quality checks

If Approve completion is available to you, review the finished work before approving it. If completion is rejected, check the rejection reason in the stage history before assigning the next action.

If the stage still shows QC pending or QC started, follow Record quality control checks.

When Mark work order finished is available, review the whole job before using it. Required stages, quality checks and trials must be complete.